Billeranga Tank
Full Roof Replacement, 2.25ML Storage Tank
Valve, Flow Meter & MSCL Pipework Upgrade.
Internal/External Concrete Repair Works.
Structural Steel, Access & Safety Upgrades.
Electrical, Instrumentation & SCADA Upgrade.
Tank Cleaning, Disinfection & Commissioning.
Hascon Civil delivered a complete refurbishment of the 2.25ML Billeranga Ground Level Tank, removing and replacing a deteriorated steel roof structure with new precast columns, steel beams, purlins and sheeting, alongside new access hatches, ventilators, guardrails and a security enclosure.
The scope extended well beyond the roof - internal and external concrete repairs restored the tank structure itself, while new DN200 valves, a dismantling joint and a magnetic flow meter were installed on the existing pipework, backed by electrical, instrumentation and SCADA upgrades to bring the asset's control systems up to current standard.
The project closed out with full tank cleaning, disinfection and commissioning, demonstrating Hascon Civil's ability to manage structural, mechanical and electrical disciplines under one roof on a single, tightly sequenced program.