Aurelian Street Valve Replacement
Installation of New DN600 Valves
MSCL Welding
Re-built Concrete Chamber to Match New Pipework
Asphalt, Kerb and Concrete Reinstatement
Hascon Civil replaced two trunk main valves housed within a confined 5m × 3m concrete chamber, partially demolishing the structure to remove the existing valves, install new MSCL spools, and convert the arrangement to direct-buried.
Before any permanent works began, our team completed a full site investigation and Quality Level A service location to AS 5488, using electromagnetic locating, GPR and vacuum excavation to expose the existing mains and chamber, confirming pipe alignment, clearances and constructability with certainty rather than assumption.
With that verified data feeding directly into the construction methodology, works proceeded under a managed live-main shutdown alongside coordinated traffic and noise management, keeping the site safe and compliant with both Water Corporation and City of Melville requirements throughout.